Skip to content

The case

The application that gets picked.

An aged 100 MWdc farm.

The interconnect approval queue decides who wins compute capacity — not GPUs. Undifferentiated 50 MW interconnect filings wait. You are not buying solar. You are buying an existing grid connection and filing a load the operator can say yes to. Texas (Pecos) is the worked example. The same two clocks exist on every grid: power out, and permission to pull power in after dark.

CFO
Economics

$150M/year on 50 MW. +$42M on 64 MW. +$54M on 82 MW. Recip 22 MW.

CTO
Cooling & generation

50 MW holds on the hottest design day. 54 MW is the modeled meter draw at PUE 1.08, not a site cap — versus 62.5 MW at PUE 1.25.

Counsel
Permitting

Use the generation permit you already have. Dirty cap 54 MW unchanged. Recip 22 MW.

How the filing stays inside a permit you already have.

One way in

An aged 100 MWdc farm.

Fastest time to compute

Existing PV farm

50 MW IT per 100 MWdc

Buy or retask a 2012–2021 plant. The generation interconnect is already permitted. Overlay cooling on 10% of tables — radiator tables, not a new chiller yard. Remaining PV stays generation. Drop in modular AI. Pecos is the worked example; the same screen applies wherever a large remote array is already connected.

Same 100 MWdc fence

Later phases stay on that farm

+50 MW AI · PUE 1.25 1.08

Phase 2 books TES and +14 MWe — 64 MW. Phase 3 extra halls +18 MWe — 82 MW. Recip 22 MW. Dirty cap 54 MW. Same generation permit. Same interconnect. No new water right. No new chiller-yard air permit.

Water
Closed loops. No new evaporative right on a campus you already run.
Noise and air
Pumps, not a new chiller yard. If engines are needed, TES/ORC first so shaft is ~22–28 MW — the plant an air permit will consider, not a 54 MW yard.
Envelope
Stay inside the MW you already interconnect. PUE 1.25 → 1.08. More IT, same grid connection.

Grid clock — Texas is the named example

Grid-tied first. Islanded backup if overnight service is delayed.

A generation interconnect is not a load service. That split exists on every wholesale market. ERCOT West Texas is the named farm example: 50 MW of IT draws 54 MW at the meter at PUE 1.08 — modeled facility load, not a site cap — under a 75 MW large-load threshold. Overnight is a new request. If a 54 MW engine yard will not permit, recip stays 22 MW. Phase 3 still spends +18 MWe on extra halls inside that dirty cap. Campus +47 MW inside 375 MW is the other example.

If the grid operator…The siteGrid MWTime
Approves firm overnight service for 54 MWStay grid-tied. Cooling overlay only. No on-site engines.54Months–~18 months
Approves interruptible or flexible service onlyGrid by day. Islanded generation covers the night.0–54Overlay now; engines if required
Overnight study is delayed in the large-load queueIslanded operation. 50 MW of IT still runs.0Overlay plus generator permit — not a new generation interconnect
The alternative is a greenfield hallStill an overnight study, often a new line. Same 54 MW, no existing interconnect.54Years if transmission is new

Texas figures. The same pattern holds on other grids: stay under that market’s large-load threshold where it exists. Heat recovery keeps a backup generator plant smaller — about 22 MW in summer and 28 MW in winter, not a 54 MW engine yard. That residual plant is what air, noise, and water will consider. Growth past 50 MW is recovered heat, not a bigger stack.

Permitting and economics per additional MW of AI

Capex, water, noise, air, and time are the same decision. Cooling-first reuses a permitted interconnect and avoids a new chiller yard. Time is to additional IT, not to a greenfield campus. Texas is the worked example; the comparison holds on other grids.

Path$M / AI MWFuel exposureGen. waterCooling waterTimeEmissions / noise
Komorebi cooling-first$0.72–0.78MLowNone addedLow6–12 moLow
Reciprocating gas engines$1.5–2.2MMediumMedium–highMechanical cooling12–24 moMedium
Komorebi full platform$3.2MLowNone addedLowStagedLow
Aeroderivative simple-cycle GT$3.2–4.6MHighHighMechanical cooling24–36 mo+High
Fuel cells$4.9–8.0MHighLowSite cooling still required18–30 moLow stack, fuel upstream

Reciprocating engines are typically more efficient than simple-cycle aeroderivative turbines. Combined-cycle GTs are not in this table. Fuel-cell generation-side water is Low in normal operation.

Why the overlay beats a new plant

  • Lower capex per additional MW of AI than recips or simple-cycle GTs — and no new water right or chiller-yard air permit
  • Reuses the interconnect and land you already have, or makes a campus you already permit hold more IT
  • The array stays PV. A 50-acre radiator reservation is the 24/7 cooling plant — then AI compute on the interconnect you already have
  • If overnight service is delayed — or the air permit cannot take 54 MW of engines — Phase 2 TES/ORC is already in, so the islanded plant is ~22–28 MW, not a 54 MW engine yard
Request the briefing pack

Example cover letter

A load the operator can say yes to.

Illustrative letter. Names are fictional. The operating facts are the Pecos case: 50 MW of IT at an existing solar interconnection, peak import 54 MW — under ERCOT’s 75 MW Large Load threshold.

Sierra Mesa Computing, LLC

Grid and Energy

2200 Post Oak Boulevard, Suite 1400
Houston, Texas 77056

28 August 2026

Interconnecting Transmission Service Provider
Copy: Director, Resource Integration
Copy: Director, System Planning
Electric Reliability Council of Texas, Inc.
8000 Metropolis Drive, Building E, Suite 100
Austin, Texas 78744

Copy: Qualified Scheduling Entity for Sierra Mesa Computing

Re: Co-located computing load under 75 MW — Mesa Flats Solar, Pecos County, Texas.
Load Information Form and request for TSP coordination.

Dear Sir or Madam:

Sierra Mesa Computing, LLC requests interconnection of 50 MW of computing load co-located with Mesa Flats Solar, an existing Generation Resource in Pecos County. Peak demand at the point of interconnection is approximately 54 MW, including site auxiliary. Enclosed is the Load Information Form for co-located load under 75 MW, for coordination by the interconnecting TSP and ERCOT.

This is a differentiated load addition at an existing generation interconnection. The plant is already in service. The hall uses power the array is already producing. Peak import remains below ERCOT’s 75 MW Large Load threshold. The load will be registered as a Controllable Load Resource.

Interconnection
Existing, energized generation POI. Co-located with the solar resource and battery already at the site. No new transmission line and no new generation interconnection.
Peak demand
50 MW of contracted computing load. About 54 MW at the meter with auxiliary. Below the 75 MW Large Load threshold.
Day / night
During solar hours the hall is served from the existing array; net interchange at the POI falls. Overnight import is a bounded 54 MW service.
Water
Closed-loop, air- and ground-coupled cooling. Negligible makeup. No evaporative towers. No community potable water for cooling. No new water right.
Noise
Heat rejection is distributed across the existing tracker field. No new cooling-tower cell and no new chiller yard. Operating sound is pumps and a dry-cooler fail-safe, in keeping with the solar plant already there.
Emissions
Grid-tied operation uses no on-site combustion. If the site later islands, on-site generation is about 22 MW in summer and 28 MW in winter — residual after solar, storage, and recovered heat — not a 54 MW engine plant. That is roughly half the air-permit, noise, and fuel envelope.
Load reduction
The load will respond to ERCOT instruction as a Controllable Load Resource, including curtailment and ramping consistent with Protocols for loads 25 MW or greater. The battery at the POI will be offered through our QSE for ancillary services ERCOT already procures.
Islanding
The electrical and thermal design allows the 50 MW hall to run islanded if firm overnight service is not available on the customer’s schedule. Islanding is an option. It is not required to energize the load.

We request that the interconnecting TSP coordinate this addition as co-located load under 75 MW, identify any studies required before energization, and confirm the path with ERCOT Resource Integration. We will provide the load model applicable to facilities 25 MW or greater, and any water, cooling, and community-impact information the Commission or ERCOT requests of computational load.

We are prepared to brief the TSP and ERCOT on the net-interchange profile, controllable-load capability, and the closed-loop cooling design.

Respectfully submitted,

Alexandra V. Chen

Vice President, Grid and Energy

Sierra Mesa Computing, LLC

Enclosure: Load Information Form — co-located load under 75 MW
cc: Qualified Scheduling Entity

Modeled on ERCOT’s Load Information Form for co-located load under 75 MW. The interconnecting TSP files with ERCOT. Names are fictional.