Existing PV farm
Existing land, interconnection, and 100 MWdc+ PV. Dual-purpose the array as a 24/7 cooling asset. Modular compute plus the same thermal plant. Optional CSP, TES, and ORC. Then qualified heat recovery. No field expansion.
Platform
Komorebi reduces cooling parasitics, recovers rejected heat, and returns electrical headroom to AI compute. Two starting conditions converge on one thermal platform — without an equivalent new generation interconnect. Overnight load is still a filing. Start compute first; add each thermal layer only when its incremental compute value exceeds its cost.
Existing land, interconnection, and 100 MWdc+ PV. Dual-purpose the array as a 24/7 cooling asset. Modular compute plus the same thermal plant. Optional CSP, TES, and ORC. Then qualified heat recovery. No field expansion.
Existing compute and power envelope. Needs adjacent land — ideally with PV already installed. Ambient-air, buried-loop, and cold-storage cooling first. Additional compute on the existing generation interconnect next. Optional AI heat recovery after uptime isolation. Qualified generator recovery last.

Cooling first
An ambient air and ground-coupled cooling network and cold storage cut the electrical burden of conventional heat rejection. That parasitic reduction is what creates room for additional IT load on an already-interconnected site.
Original dry coolers are retained and later shifted onto ORC condenser duty, so cooling CAPEX is reused rather than stranded.
Cooling first unlocks the most compute, soonest — at the interconnect you already have.
AI heat recovery comes after uptime isolation. It is real, and it is the smaller step.
Qualified generator recovery is last. Each asset is integrated only when it pays.
Phase 0
Months, not years
Start workloads while the platform is built
Phase 1
6–12 months
Full IT load cooled. PUE falls.
Phase 2
After uptime isolation
Useful heat recovered from AI load
Phase 3
Asset-by-asset, when it pays
Additional hours from qualified generator heat
300 MW existing IT / PUE 1.25 campus / 1,000-acre envelope, Pecos, Texas. Envelope planning case: ~130.2 MWdc PV and 50 MWth CSP on exactly 1,000 acres. 300 × 1.25 = 375 MW campus, closed envelope. Phase 1: 51 MW freed ÷ 1.08 = +47 MW IT. Grid never exceeds 375 MW.
Second named case: convert an existing 100 MWdc PV farm on the land it already occupies. This is not the 300 MW campus. Same acres. Higher-density bifacial modules (~95 MWdc). Recovered rows become ~94 MWth of CSP. No new solar land.
See the conversion case on Economics.Revive PV
Repowering an existing PV farm should not start with a dumpster. Recover what can run. Recycle what cannot.
01
On-site take-down and triage. What can run stays in the loop.
02
Inspect, recoat, repair, and test in a two-container mobile factory.
03
Put recovered modules back to work. Recycle the rest.