Skip to content

Platform

Cooling-first infrastructure on land that is already connected.

Komorebi reduces cooling parasitics, recovers rejected heat, and returns electrical headroom to AI compute. Two starting conditions converge on one thermal platform — without an equivalent new generation interconnect. Overnight load is still a filing. Start compute first; add each thermal layer only when its incremental compute value exceeds its cost.

Existing PV farm first. Constrained campus second.

Existing PV farm

Existing land, interconnection, and 100 MWdc+ PV. Dual-purpose the array as a 24/7 cooling asset. Modular compute plus the same thermal plant. Optional CSP, TES, and ORC. Then qualified heat recovery. No field expansion.

Constrained AI campus

Existing compute and power envelope. Needs adjacent land — ideally with PV already installed. Ambient-air, buried-loop, and cold-storage cooling first. Additional compute on the existing generation interconnect next. Optional AI heat recovery after uptime isolation. Qualified generator recovery last.

Modular compute halls on already-connected solar land

Cooling first

The thermal layer is the compute unlock.

An ambient air and ground-coupled cooling network and cold storage cut the electrical burden of conventional heat rejection. That parasitic reduction is what creates room for additional IT load on an already-interconnected site.

Original dry coolers are retained and later shifted onto ORC condenser duty, so cooling CAPEX is reused rather than stranded.

Commercial sequence

  • 01

    Cooling first unlocks the most compute, soonest — at the interconnect you already have.

  • 02

    AI heat recovery comes after uptime isolation. It is real, and it is the smaller step.

  • 03

    Qualified generator recovery is last. Each asset is integrated only when it pays.

  1. Phase 0

    Existing campus

    Months, not years

    • Fast-deploy generation and modular halls
    • Independent rack cooling
    • Fail-safe heat-rejection bypass
    • Uptime is the first commercial gate

    Start workloads while the platform is built

  2. Phase 1

    Cooling first

    6–12 months

    • Ambient air and ground-coupled cooling loops
    • Cold storage; conventional cooling retained
    • Independent of PV densification on a campus
    • On existing PV farms: GCCM reflective foundations and array densification

    Full IT load cooled. PUE falls.

  3. Phase 2

    AI heat recovery

    After uptime isolation

    • Heat pumps plus thermal ladder
    • TES and right-sized ORC
    • Original dry coolers reused for ORC condenser duty
    • Failure isolated from rack cooling; no later stage may degrade Stage 1

    Useful heat recovered from AI load

  4. Phase 3

    Qualified generator recovery

    Asset-by-asset, when it pays

    • Qualified reciprocating or simple-cycle heat into the existing TES/ORC stack
    • Asset-by-asset — only where recoverable heat and OEM/EPC interfaces justify integration
    • Not every generator topology qualifies
    • No solar-land expansion

    Additional hours from qualified generator heat

Pecos Campus Case

300 MW existing IT / PUE 1.25 campus / 1,000-acre envelope, Pecos, Texas. Envelope planning case: ~130.2 MWdc PV and 50 MWth CSP on exactly 1,000 acres. 300 × 1.25 = 375 MW campus, closed envelope. Phase 1: 51 MW freed ÷ 1.08 = +47 MW IT. Grid never exceeds 375 MW.

050100150Phase 0Existing+47 MWPhase 1Cooling+11 MWPhase 2AI heat+74 MWPhase 3Generators0 MW58 MW132 MW
Added this phaseCumulative additionalY-axis: MW
300 × 1.25 = 375 MW grid envelope. Phase 1: 51 MW freed ÷ 1.08 = +47 MW IT. Then +132 MW / +44% at PUE 1.04. Phase 3 +74 MW is new on-site MWe, not a second helping of cooling savings. Off-grid, cooling avoids ~91 MW of generator nameplate (449 vs ~540).

100 MWdc Existing PV Farm Conversion Case

Second named case: convert an existing 100 MWdc PV farm on the land it already occupies. This is not the 300 MW campus. Same acres. Higher-density bifacial modules (~95 MWdc). Recovered rows become ~94 MWth of CSP. No new solar land.

See the conversion case on Economics.

Revive PV

Aging modules become a recoverable asset.

Repowering an existing PV farm should not start with a dumpster. Recover what can run. Recycle what cannot.

  1. 01

    Remove

    On-site take-down and triage. What can run stays in the loop.

  2. 02

    Repair

    Inspect, recoat, repair, and test in a two-container mobile factory.

  3. 03

    Redeploy

    Put recovered modules back to work. Recycle the rest.

Walk a site through the sequence.