Skip to content
Dappled forest light opening onto an existing solar field and modular AI halls

More Compute. Naturally.

Komorebi · (ko-moh-ray-bee)

More AI compute. On the PV array you already have.

Most of the field keeps making power. A slice of it takes the heat. Those freed megawatts go to GPUs, not chillers.

A cooling overlay on a plant that already exports — not a new power plant, and not a new interconnect. Cooling tables on a slice of the field. The rest stays PV. Dry coolers remain as backup.

  • Existing solar plant. Cooling tables on a slice of the field. The rest keeps making power.
  • 50 MW of firm computers on the connection you already have.
  • Cooling uses 8.5 MW less than chillers. Dry coolers stay as backup.

The worked case is 50 MW of firm IT on an existing 100 MWdc PV farm. Cooling uses 8.5 MW less than chillers, so the meter reads 54 MW, not 62.5.

Phase 1 — 50 acres of radiator tables on an existing PV fencelinePER MWp · WEST TEXAS PLANNING CASE1 MWp PV ARRAYTRACKER ROWS=3.5 × 200-TON CHILLERS200 TON200 TON200 TON200 TONENABLED COMPUTE VALUE~$1.5M / YEAR$1.5M firm · 50 MW / 100 MWdcOn the interconnect you already haveHall closed · $0.72–0.78M / MW of firm ITvs $3M / MW-yr planning value of 99.9% firm IT

A cooling overlay on the fenceline you already have. Closing 50 MW of firm IT is $36–39 million — $0.72–0.78M per MW — against $150 million per year of planning offtake. Two comparisons: an already-connected solar deed becomes a 50 MW IT host this year; 8.5 MW less parasitic load versus PUE 1.25 at the same 50 MW. Original dry coolers stay as fail-safe.

Phase 1

Existing large PV farms in leading economies

~91 GW

AI compute these farms’ dual-use can host

Hybrid radiator tables and a heat-pump cold bank. 50 MW of design-target 99.9% firm AI per 100 MWdc.

Phase 2 / 3

Same land

~116 GW

Optional on the same land

TES/ORC and recovered-row CSP after Phase 1. Engines last. Not in the Phase 1 offtake. Peak / flexible ~149 GW. Qualifying plants, not signed contracts.

See your screened national set

Pecos planning case

The worked case is 50 MW of firm IT on a 100 MWdc farm

100 MWdc legacy farm / 50 MW firm IT / 8.5 MW parasitic cut / 500-acre 2015 fence. Phase 1 books 50 MW at the interconnect you already have. TES/ORC and extra halls are later, on the same fence.

Grid100 MWdc farm50 MW firm ITAI compute50 MW ITAI heatrecoveryFrom serversEngineheat recoveryOn-siteCoolingAir + ground+50 MW+100%SITE COMPUTE6–12 monthsCumulative +50 MWPUE 1.251.08Parasitics 12.54 MW (7% of meter)WUE 0.000.00 L/kWh · 0 0 Mgal/yrElectricityHeatCooling

50 MW firm IT. 8.5 MW parasitic cut (12.5 → 4 MW). Meter 54, not 62.5.

0255075100Phase 0Existing+50 MW8.5 MWPhase 1Cooling+14 MWPhase 2AI heatrecovery+18 MWPhase 3Engine heatrecovery0 MW64 MW82 MW
Added this phase8.5 MW parasitic recoveryCumulative additionalY-axis: MW
50 MW firm, then 64 MW, then 82 MW on the same 100 MWdc fence. Phase 1 bar splits 8.5 MW of parasitic recovery (12.5 MW of compressors to 4 MW of pumps) from the rest of the 50 MW hall. Meter 54, not 62.5. Phase 2: TES/ORC +14 MWe. Phase 3: extra halls +18 MWe. Recip 22 MW. Dirty cap 54 MW.

Pecos, Texas planning weather

Comparative parasitic load across the year

Monthly mean MW. Lower is better. Cooling parasitics at each architecture on the same 50 MW hall. Shape from 2024 NSRDB for Pecos; means scaled to 12.5 MW at PUE 1.25 and 4 MW at Komorebi Phase 1.

00%510%1020%1530%2040%Parasitic load (MW)% of 50 MW hallJanFebMarAprMayJunJulAugSepOctNovDec
  • Komorebi Phase 14 MW · 8% · PUE 1.08
  • Dry cooler + adiabatic9 MW · 18% · PUE 1.18
  • Dry cooler + chiller12.5 MW · 25% · PUE 1.25

Not gigawatts. The source files labeled monthly-mean MW as GWe. Scaled so the chiller line is the 12.5 MW PUE 1.25 block on a 50 MW hall. Komorebi is Phase 1 only — 50 acres of radiator tables — not later recovery.

100%

More AI compute per 100 MWdc — inclusive of the 8.5 MW parasitic cut. Weather and soils set the acres.

Existing

At the same interconnect

50 MW

Pecos planning case baseline

474 sites

U.S. existing-PV screen

Named case: 50 MW firm IT on 100 MWdc, inclusive of 8.5 MW parasitic recovery. Weather and soils set the acres. Pecos planning case100 MWdc legacy farm / 50 MW firm IT / 8.5 MW parasitic cut / 500-acre 2015 fence.

Three insights

Three insights. Four constraints. One platform.

The bottleneck in hyperscale AI is no longer compute demand. It is time-to-energy.

01

Convert capacity into compute

AI growth is limited by power delivered to servers and heat removed — not by nameplate generation alone.

02

Integrate the resources

Cooling, recovered heat, CSP, thermal storage, and ORC reinforce one another as one system.

03

Stage the investment

Add each capability only when its incremental compute value exceeds its incremental cost.

Four constraints. Infrastructure has not caught up.

Growth is constrained by the infrastructure required to support it — not by demand for servers.

Electrical

Limited interconnect capacity and substation availability delay or cap growth.

Fuel

Additional natural-gas supply, infrastructure, and permitting are slow and uncertain.

Groundwater

Cooling towers withdraw and evaporate water, creating permitting and environmental limits.

Time

New infrastructure takes years and billions — stranding racks and delaying revenue.

Why capacity is left on the table

Conventional architecture rejects the energy that could run more GPUs.

Conventional architecture

Nearly all IT electrical energy ultimately becomes heat.

  • Fuel and generation

    Scarce interconnect and turbines are spent on cooling and support loads as well as GPUs.

  • Rejected heat

    In high-temperature liquid-cooled configurations, a large fraction of that heat can be captured in the liquid loop. Komorebi models a 70°C source-loop condition — a design case, not an industry universal.

  • Groundwater loss

    Towers withdraw and evaporate water, creating permitting and environmental limits year after year.

Komorebi architecture

Phase 1 removes heat. Recovery comes later — after uptime is proven.

  • Remove heat first

    Radiator tables on extra A-frames under cooler rows only. Remaining PV stays generation. Phase 1 is simpler and faster to implement.

  • Recover heat later

    After uptime isolation, capture AI-server heat, then heat from qualified generation — each asset only when it pays.

  • Enable compute

    Return electrical headroom to IT load — without requiring an equivalent new grid interconnection or material groundwater withdrawal. Later thermal recovery can use heat from qualified existing generation.

The product

More compute from the power, heat, and land already there.

Dual-purpose an existing PV farm as 24/7 cooling, then drop in modular AI. The hyperscaler is buying additional compute on an existing generation interconnect — not an equivalent new transmission line. Heat recovery is later. Phase 1 is the hall.

Existing PV farm

Existing land, interconnection, and 100 MWdc+ PV. Dual-purpose the array as a 24/7 cooling asset. Modular compute plus the same thermal plant. Optional CSP, TES, and ORC. Then qualified heat recovery. No field expansion.

Constrained AI campus

Existing compute and power envelope. Needs adjacent land — ideally with PV already installed. Ambient-air, buried-loop, and cold-storage cooling first. Additional compute on the existing generation interconnect next. Optional AI heat recovery after uptime isolation. Qualified generator recovery last.

Modular compute halls wrapped by an existing solar field

Architecture

Remove heat first. Recover heat later.

Each layer is independently valuable. Phase 1 is the product — cooling, simpler and faster. Phase 2 is the filing and the plumbing. Phase 3 is the residual plant. No later stage may degrade rack cooling. Thermal recovery may be unavailable. Rack cooling may not.

  1. 01

    Remove

    Radiator tables and a cold bank cut parasitics. Phase 1 — simpler and faster.

  2. 02

    Recover

    After uptime isolation, capture AI-server heat, then heat from qualified generation when each asset pays.

  3. 03

    Upgrade

    Lift temperature with heat pumps and CSP only when incremental compute value exceeds cost.

  4. 04

    Enable

    Free electrical headroom for additional AI compute inside the same envelope.

Reliability principle

Thermal recovery may be unavailable. Rack cooling may not.

Opportunity set

Additional compute. Existing generation interconnect.

Candidate U.S. PV sites
474
Phase 1 AI this set can host
~21.8 GW
99.9% firm AI
$3M / MW-yr
See your screened national set

Sequence

Cooling first. Heat later. Same fence.

Start the hall. Put cooling on a slice of the tables you already have. Recover heat only after that hall is up. Foundations, optics, and offtake sit in the briefing — under NDA.

  1. Phase 0

    Existing site

    Months, not years

    • Modular halls on land you already have.
    • Cooling that can run before the overlay is finished.
    • Uptime is the first commercial gate.
    • Farm or campus — same order.

    Workloads start while cooling is built.

  2. Phase 1

    Cooling

    6–12 months

    • Radiator tables on a slice of the field. The rest stays PV.
    • Dry coolers remain as fail-safe.
    • Same fence. Same permit class.
    • This is the product.

    More IT at the interconnect you already have.

  3. Phase 2

    AI heat recovery

    After the hall is up

    • Server heat first.
    • Leftover acres take CSP.
    • Cooling does not wait on this step.
    • Optional — after uptime.

    More compute from heat the site already makes.

  4. Phase 3

    Engine heat recovery

    After heat is booked

    • Recovered heat runs more halls — not a bigger engine yard.
    • Same fence.
    • Engines last.
    • Still one overlay, not a new power plant.

    Same plant. More IT.

Platform

Four levers on the same land.

Cooling-first thermal infrastructure

Radiator tables, a cold bank, and low-water heat rejection cut parasitic load and raise compute density per available megawatt.

Fixed-footprint densification

On existing PV farms: repower legacy polycrystalline, monofacial arrays with higher-density bifacial modules on reflective foundations, recover aperture for Komorebi CSP, and add duration without expanding the site.

Duration overlay

Optional NPI 4-lens, thermal energy storage, and ORC convert leftover acres into 14 MWe — on the same radiator loop. Dry cooler is fail-safe only, not the Phase 2 sink.

Module recovery

On existing PV farms: on-site triage, refurbishment, and redeployment with Revive PV turns aging modules from a repowering liability into a recoverable asset.

How the platform works

Start with an existing PV farm.

Start with an existing PV farm of the right age. Request a solution briefing. GPS, weather, generation, and soils are shared after NDA.

Request a briefing