Economics

Cost per MW of additional compute enabled.

That is the public metric. Cooling-first does not principally generate electricity — it reduces parasitic load and releases electrical headroom. Two named planning cases.

Pecos Campus Case

300 MW existing IT / PUE 1.25 campus / 1,000-acre envelope

300 × 1.25 = 375 MW campus, closed envelope. Phase 1: 51 MW freed ÷ 1.08 = +47 MW IT. Grid never exceeds 375 MW.

100 MWdc Brownfield PV Conversion Case

50111 154 MW

50 MW initial → 111 MW 99.9% firm at maturity → 154 MW peak / flexible.

Illustrative unlock

Scale the 100 MWdc Brownfield PV Conversion Case

Linear sketch from a 100 MWdc row-field example — ~390-acre row field. Not the 300 MW campus case. Not a site model.

Fast-track compute
50 MW
Additional modeled compute
+61 MW
99.9% firm at maturity
111 MW
Peak / flexible
154 MW
Repowered PV
95 MWdc
Recovered CSP
94 MWth

Illustrative enabled-compute value, at $3.086M per incremental MW-year: $188.2M / year

Qualify this size

Incremental infrastructure per additional IT MW

CAPEX is $M per MW of additional 99.9% firm IT load enabled — the thing Komorebi sells. Fuel exposure is natural-gas burned per MWh of IT — not an efficiency grade. Reciprocating engines typically have a better heat rate than simple-cycle aeroderivative turbines; that is why recips are Medium and simple-cycle GTs are High. Water is split: generation-side versus data-center cooling. Time is to additional compute, not to a greenfield campus.

Path$M / IT MWFuel exposureGen. waterCooling waterTimeEmissions / noise
Komorebi cooling-first$1.1–1.5MLowNone addedLow6–12 moLow
Reciprocating gas engines$1.5–2.2MMediumMedium–highMechanical cooling12–24 moMedium
Komorebi full platform$2.3–3.6MLowNone addedLowStagedLow
Aeroderivative simple-cycle GT$3.2–4.6MHighHighMechanical cooling24–36 mo+High
Fuel cells$4.9–8.0MHighLowSite cooling still required18–30 moLow stack, fuel upstream

Reciprocating engines are typically more efficient than simple-cycle aeroderivative turbines. Combined-cycle GTs are not in this table. Fuel-cell generation-side water is Low in normal operation.

Indicative LCOE — $ / MWh delivered to IT load

Cooling-first lowers the cost of energy that reaches IT by cutting parasitic load. The full platform adds duration and ORC hours for 24/7 capability. Generator paths below are conventional generation LCOE.

Path$ / MWhBasis
Komorebi cooling-first$40–60Delivered to IT — parasitic reduction
Reciprocating gas engines$55–85Generation LCOE
Komorebi full platform$35–55Delivered to IT — duration and ORC hours
Aeroderivative simple-cycle GT$70–110Generation LCOE
Fuel cells$95–145Generation LCOE

Figures are from two illustrative U.S. planning cases — a Pecos Campus Case (300 MW existing IT at PUE 1.25, 375 MW campus electrical, WUE 1.5 L/kWh, 1,000-acre envelope) and a 100 MWdc Brownfield PV Conversion Case (~390-acre row field) — based on 2025 public benchmarks. Grid envelope stays 375 MW through Phase 2. Phase 1: 51 MW freed ÷ PUE 1.08 = +47 MW IT. Recovery then 1.05 → 1.04; Phase 3 campus grows only from on-site generation. Actual results vary by site, resource, fuel, interconnection, and execution. Patents pending. Not an offer.

Why the comparison favors cooling-first

Request the briefing pack